Generators are about to give way to the grid at Allied Gold Corporation’s Kurmuk gold mine in Ethiopia. State owned utility Ethiopian Electric Power, through its contractor, has begun assembling, installing and commissioning the equipment and materials for an automated grid stabilisation system, which keeps the power supply steady, at the mine of the TSX listed company.
Allied Gold calls this an important milestone in the final phase of the power infrastructure programme. Once the full power system is complete, the grid will meet the full load requirements of normal plant operation without relying on generators, ensuring a stable, full power draw that supports sustainable increases in throughput, the volume of ore the plant can process.
In parallel, the company says it continues to ramp up operations and targets further production growth, with the goal of starting gold sales in December and commercial production expected by year end. Reaching those milestones will support Kurmuk’s transition into a significant, low cost gold producing operation and the company says, a period of significantly increased free cash flow, which is the cash left after operating and capital costs.
Exploration is moving alongside. Work at Tsenge is progressing to develop it as an additional mining area and a source of ore for the mill. The Tsenge Trend, which has a known strike length of 9 km and was highlighted in the company’s 6 October disclosure, is a priority area, where multiple higher grade gold discoveries point to potential for resource growth. An initial mineral resource estimate for the Kiftet and Hiccup Hill zones is expected by the first half of 2027, drilling continues to confirm and extend the higher grade zones, and the company is preparing to start the permitting processes that future development will need. Allied Gold says the discoveries lie close to existing processing infrastructure and that Tsenge is one of several prospective opportunities across its extensive Kurmuk land package.
The timing matters because production in the early years at Kurmuk is planned above the life of mine average, as mine sequencing takes advantage of near surface, higher grade ore from the Ashashire and Dish Mountain open pits. The company says the new high grade zones at Tsenge fit its objective of finding more high grade material to sustain a long term production profile of 300 000 ounces a year.
Shareholders have been told what to expect from the cash. Allied Gold’s capital allocation priorities are continued investment in growth, including exploration and development at Kurmuk, a strong balance sheet and returns to shareholders. Those returns are expected to include a base dividend starting in 2027 and a normal course issuer bid, which is a share buyback programme, for up to 10% of the public float, subject to approval from the TSX.